PST plant from pilot to production plant

28/06/2012

ARN’s PST plant has recently been transformed from pilot to production plant. The capacity has grown enormously and the plant expects to process a daily capacity of no less than 170 tonnes per day in 3 months’ time. The plant’s target to achieve 95% recycling of old cars in 2015 therefore lies within reach.

Operator training
“We have just started training a second group of operators”, says Hans van de Greef, director of the PST plant. “This is going to allow us to run 16 hours a day in different shifts with an increase in capacity to 170 tonnes per day. The training lasts three months. When it is finished, we will have a team of 17 people in total.”

Test batch
“Actually, almost everything in the facility is working fine, except fibre reprocessing”, according to Van de Greef. “And we are getting a better grip on things there too. A test batch employing fibre reprocessing has been sent to a customer – a water authority in Germany – for checking. The results will allow us to adjust the module further, so that it will soon operate optimally.”

PST-fabriek

Back to overview

ARN Recycling

ARN Recycling Services